Preconstruction Services

Preconstruction services lay the groundwork for well-run construction projects. BROR’s preconstruction team implements a series of services before construction begins to alleviate potential challenges to your budget and schedule. Our industry experts will help you plan a cost-effective and timely construction plan that facilitates a more streamlined building process. Everything we do is designed to increase speed-to-market, control costs, and improve productivity. Our preconstruction services deliver accurate pricing and scheduling that minimize construction gaps, ensuring your project is on schedule and within budget. Our project managers are the best in the business, taking ownership of the project and ensuring a successful transition to the construction phase. We also offer private provider services for plan reviews to expedite the permit processing time with the building departments, reduce the number of submittals and perform timely inspections.

BROR Construction logo: gold text and icons within an octagonal frame on black.

Design-Build Process

Architectural sketch of a multi-story building with balconies, trees, and landscaping along a street.

Research

Pre Design

1-3 weeks

  1. Client Contact
  2. Gather Property Info (survey, soil test, reports, MLS info)
  3. Create Preliminary Site Plan
  4. Create Preliminary Construction Budget
  5. Create Design-Build Agreement
  6. Sign Design Build Agreement

Deliverables:

  • Preliminary Site Plan
  • Rough Construction Budget
  • Design-Build Proposal

$2,500

Design & Documentation

Schematic Design

2-4 weeks

  1. Project Kickoff
  2. Obtain Property Info
  3. Layout, areas, space usage
  4. Analysis of req'd codes
  5. Code compliance review with MEP Engineers
  6. Review & Approve Final SD Set
  7. Submit Preliminary SD & Site Plan for Pre-Development Meeting with City

Deliverables:

  • Floor Plan
  • General Site Plan
  • Preliminary Elevations
  • 3D Rendering (optional)

$2,500

Design Development

3-7 weeks

  1. Refine Floor Plan & Space Usage
  2. Further Development of Civil Engineering Plans
  3. Development of Structural Systems (exterior walls, roofs, windows, doors)
  4. Further Development of MEP Systems
  5. Review & Approve Final DD Set

Deliverables:

  • More Detailed Set of Drawings
  • Finishes & Product Selections
  • Updated Budget

$5,000

Construction Documents

5-8 weeks

  1. Final Design of Contract Docs Including Specs & Materials
  2. Final Coordination of Civil, Arch, & MEP Designs
  3. ADA/TAS Compliance Review
  4. Meet for Final CD Set Approval
  5. Submit for Permitting
  6. Coordinate Permit Approval Process w/ City & Design Team

Deliverables:

  • Complete Set of Construction Drawings to Submit for Local Authority Approvals

$5,000

Research

Pre Design

1-3 weeks

  1. Client Contact
  2. Gather Property Info (survey, soil test, reports, MLS info)
  3. Create Preliminary Site Plan
  4. Create Preliminary Construction Budget
  5. Create Design-Build Agreement
  6. Sign Design Build Agreement

Deliverables:

  • Preliminary Site Plan
  • Rough Construction Budget
  • Design-Build Proposal
  • 

Design & Documentation

Schematic Design

2-4 weeks

  1. Project Kickoff
  2. Obtain Property Info
  3. Layout, areas, space usage
  4. Analysis of req'd codes
  5. Code compliance review with MEP Engineers
  6. Review & Approve Final SD Set
  7. Submit Preliminary SD & Site Plan for Pre-Development Meeting with City

Deliverables:

  • Floor Plan
  • General Site Plan
  • Preliminary Elevations
  • 3D Rendering (optional)

Design Development

3-7 weeks

  1. Refine Floor Plan & Space Usage
  2. Further Development of Civil Engineering Plans
  3. Development of Structural Systems (exterior walls, roofs, windows, doors)
  4. Further Development of MEP Systems
  5. Review & Approve Final DD Set

Deliverables:

  • More Detailed Set of Drawings
  • Finishes & Product Selections
  • Updated Budget

Construction Documents

5-8 weeks

  1. Final Design of Contract Docs Including Specs & Materials
  2. Final Coordination of Civil, Arch, & MEP Designs
  3. ADA/TAS Compliance Review
  4. Meet for Final CD Set Approval
  5. Submit for Permitting
  6. Coordinate Permit Approval Process w/ City & Design Team

Deliverables:

  • Complete Set of Construction Drawings to Submit for Local Authority Approvals


'

Pricing

Bid Proposal

3-5 weeks

  1. Release Final CD Set for Pricing
  2. Develop Scopes of Work for All Trades
  3. Answer RFI's Through Bidding Process
  4. Scope Verification & Subcontract Qualification
  5. Prepare Bid Proposal
  6. In Person Proposal Review
  7. Sign Construction Contract

Deliverables:

  • Contractual Pricing
  • Scopes of Work
  • Scope Verification
  • Bid Proposal
  • Construction Contract

Construction

Construction Management

  1. Submit Permit Application
  2. Issue Subcontract Agreements
  3. Develop Construction Schedule
  4. Order Long Lead Items
  5. Coordinate Preconstruction Meetings
  6. Mobilize and Start Construction Phase

Deliverables:

  • Construction Mobilization